Where all of this
came from.
Sources are grouped by how much weight they deserve. A regulator's record of what was actually filed outranks a press release about the same project — and a press release outranks an article about the press release.
Source hierarchy used on this site
- Alberta Utilities Commission — what was actually applied for and what has been decided
- AESO — system-level facts about the grid and the connection queue
- Municipal government — local land-use and planning processes
- Government of Alberta — Major Projects listings, strategy and regulation
- Official company disclosures — design and investment claims, labelled as company claims
- Filed project documents
- Statistics and international bodies
- Technical references — for general engineering context only
- Strong independent journalism — for context, criticism and figures not published elsewhere
Promotional material is never used for a technical claim where a regulatory filing exists.
Regulator
- Alberta Utilities Commission accessed 2026-08-17Beacon AI Centers – Indus Project Thermal Power Plant (Proceeding 30524) ↗
3 claims rest on this source
- 1,494 MW Proposed total generating capability
- ~1,200 MW Supply to co-located data halls, normal operation
- 18 August 2026 AUC oral hearing commences
- Alberta Utilities Commission accessed 2026-08-16Synapse Data Center Power Plant Project (Proceeding 30732) ↗
4 claims rest on this source
- ~1,400 MW Proposed combined-cycle natural-gas capacity
- 1,800 MW Proposed emergency / backup diesel generation
- Not connected Connection to the Alberta Interconnected Electric System
- Process suspended pending further information requests Proceeding status
System operator
- Alberta Electric System Operator published 2025-06-04 accessed 2026-08-16AESO announces interim approach to large load connections ↗
4 claims rest on this source
- 29 Proposed large-load projects seeking grid connection
- > 16 GW Total capacity sought by those connection requests
- 1,200 MW AESO interim Phase 1 large-load connection limit
- ~1,400 MW AESO illustrative comparison: load of the City of Edmonton
Municipal government
- Sturgeon County published 2026-07 accessed 2026-08-16News release — Meta makes historic investment in Alberta ↗
- Rocky View County accessed 2026-08-16Beacon AI Hub — Thermal Power Plant Application / Area Structure Plan ↗
Provincial government
- Government of Alberta — Major Projects accessed 2026-08-16Meta Data Center, Sturgeon County ↗
5 claims rest on this source
- 1 GW Announced facility scale
- $13B+ Announced investment
- ~1.8 GW Possible full campus build-out figure
- 3,000+ Peak construction workforce
- 300 Permanent operational jobs
- Government of Alberta — Major Projects accessed 2026-08-16Beacon Heartland Artificial Intelligence Hub ↗
1 claim rest on this source
- 960 MWe Proposed total capability
- Government of Alberta — Major Projects accessed 2026-08-16Technologies New Energy / Data District Data Centre — Phase 1 ↗
2 claims rest on this source
- 240 MW Phase 1 combined capacity across four facilities
- $1.26B Phase 1 combined development budget
- Government of Alberta accessed 2026-08-16Artificial intelligence data centres strategy ↗
- Government of Alberta accessed 2026-08-16Powering new pathways for data centres (Bill 8 / Utilities Statutes Amendment Act, 2025) ↗
- Government of Alberta — Open Government accessed 2026-08-16Data Centre Regulation 117/2026 ↗
- Government of Alberta accessed 2026-08-16Taxes and levies overview ↗
Company disclosure
- Meta published 2026-07 accessed 2026-08-16Breaking ground on Meta’s first data center in Canada ↗
2 claims rest on this source
- ~1,750 acres Campus land area
- ~2.9M ft² Facility floor space
- Meta Data Centers published 2026-07 accessed 2026-08-16Hello, Sturgeon County! ↗
International body
- United Nations accessed 2026-08-16Global Digital Compact ↗
- United Nations accessed 2026-08-16The 17 Sustainable Development Goals ↗
Technical reference
- NVIDIA accessed 2026-08-16NVL72 AI Factory Enterprise Reference Architecture — Components ↗
1 claim rest on this source
- ~142 kW Illustrative modern AI rack power
- This website accessed 2026-08-16Arithmetic performed on published figures (methodology shown with each claim)
5 claims rest on this source
- ~7.08 km² Campus land area, converted
- ~269,000 m² Facility floor space, converted
- 7,140 m² Area of one standard football pitch
- ≈ 992 Meta campus land, in football pitches
- ≈ 38 Meta facility floor space, in football pitches
Journalism
- Global News / The Canadian Press published 2026-07-10 accessed 2026-08-16Meta data centre in Alberta to start up ahead of adjacent Greenlight power plant ↗
3 claims rest on this source
- 970 MW Phase 1 grid allocation
- 932 MW Greenlight Electricity Centre generating capacity
- 250 MW Capital Power long-term supply agreement
What this site does not claim
- That every announced project will be built.
- That the published megawatt figures can be added together.
- That community concerns raised in a hearing are proven impacts.
- That a developer's statement about its own project is an independent finding.
- That the illustrative build-out scenarios are forecasts.
- That any Alberta project uses the illustrative NVIDIA hardware referenced on this site.